Monday, 12 November 2012

It was always expected to be a messy start to the job in the fact that we encountered deep basements from previous buildings which had been demolished before Wates started on the project. A re-design on the upper plot meant a prolonged start however TKL managed to gain a few days coming into November. Unfortunately on the lower plot we again came across old basement which meant deeper than expected foundations. These had to be cast at a lower level then built up in mass blockwork to the underside of block and beam.
Storage of site materials is proving to be difficult due to the size of the site however the neighbour has been very helpful in letting us access our site through his land temporarily. On 12th November we will be placing block and beam floors.
 
 


 