Friday, 22 February 2013

This week has been productive with good progress being made with 2nd fix joinery and 2nd fix M&E, which has allowed kitchens to be fitted in the remaining units. Mid week we welcomed the tilers to site who completed their work in the bathrooms and kitchens of the 1st two plots.




 

Tuesday, 19 February 2013

This week the scaffold was successfully dismantled and taken off site freeing up much needed space enabling the ground works to commence their final phase early next week.
 

 
Internally the joinery 2nd fix is progressing well and architraves, skirting and kitchens have been fitted to half the units.
 
 
 
 

Friday, 8 February 2013

At the beginning of this week the bricklayers put the finishing touches to the masonry, leaving four days for all the other jobs externally to be completed as the scaffold drop is scheduled for Monday.
 
 
Once again on the Upper Road project we have been fortunate with the weather, enabling us to complete as planned, the render to both roof step details.
 
 
Bird boxes installed.
 
 
 

Friday, 1 February 2013

Now that the walls are completely sealed and closed the Joiners have started installing Window boards & doors casings part of their first fix, as they moved from one unit to the next the plasterers replaced them.