Friday, 1 March 2013

Internal works continued this week with low level tiling to boxing in bathrooms.

 
The joiners 2nd fix moved onto the MVHR boxings.
 

Externally the ground workers started on the Upper Road and west elevation setting levels in preparation for the paving slabs and pouring the concrete for the cycle store base.


At the end of the week a start was made on laying the paving slabs and spreading out of the first delivery of top soil.
 

 
 

Friday, 22 February 2013

This week has been productive with good progress being made with 2nd fix joinery and 2nd fix M&E, which has allowed kitchens to be fitted in the remaining units. Mid week we welcomed the tilers to site who completed their work in the bathrooms and kitchens of the 1st two plots.




 

Tuesday, 19 February 2013

This week the scaffold was successfully dismantled and taken off site freeing up much needed space enabling the ground works to commence their final phase early next week.
 

 
Internally the joinery 2nd fix is progressing well and architraves, skirting and kitchens have been fitted to half the units.
 
 
 
 

Friday, 8 February 2013

At the beginning of this week the bricklayers put the finishing touches to the masonry, leaving four days for all the other jobs externally to be completed as the scaffold drop is scheduled for Monday.
 
 
Once again on the Upper Road project we have been fortunate with the weather, enabling us to complete as planned, the render to both roof step details.
 
 
Bird boxes installed.
 
 
 

Friday, 1 February 2013

Now that the walls are completely sealed and closed the Joiners have started installing Window boards & doors casings part of their first fix, as they moved from one unit to the next the plasterers replaced them.

Friday, 25 January 2013

The 1st fix M&E is now completed in all four units and insulation has been added to the walls which were then closed up with the commencement of 2nd fix dry lining.
 

 

Friday, 18 January 2013

Up until this week the stone work was progressing steadily through the final lift, first floor to eaves...then the temperate took a nose dive. When this happens there is nothing anyone can do, with the mercury dropping to the depths it has this week all work must stop. On the bright side everyone on site got the chance to wear all their new Christmas socks all at once on the same day!


The shocking cold snap didn't deter work from progressing inside plots 1-4 on
Upper Road and Acoustic Floors were laid.


The internal wall have now all gone up.  



As soon as all the walls were up a start was made on the electrics and plumbing also known as 1st fix M & E