Friday, 18 January 2013

Up until this week the stone work was progressing steadily through the final lift, first floor to eaves...then the temperate took a nose dive. When this happens there is nothing anyone can do, with the mercury dropping to the depths it has this week all work must stop. On the bright side everyone on site got the chance to wear all their new Christmas socks all at once on the same day!


The shocking cold snap didn't deter work from progressing inside plots 1-4 on
Upper Road and Acoustic Floors were laid.


The internal wall have now all gone up.  



As soon as all the walls were up a start was made on the electrics and plumbing also known as 1st fix M & E