Monday, 10 December 2012

Treacherous weather conditions could have easily turned into treacherous working conditions without close attention being given to all areas on site this week. In between the periods of high winds, frost and black ice work was safely and successfully carried out in the following areas:
 
The felt and batons to both roofs
 
 
Slates were fitted towards the latter end of the week
 

 
The ground floor windows were installed
 

Stone work commenced
 
 
As the build continues through the wet winter months the completion of the work this week has been crucial as the building is now water tight, meaning the internal trades can now start next week.